Proposed process towards taking 1.1 to final #687

@jogu

Description

@jogu

My personal suggestion on timeline - we need to discuss/agree this in the WG, and the months are "indicative", we don't generally commit to deadlines.

Feb:

  • Finish spec work (there's known breaking changes to IAE needed/security issues that need to be sorted & feedback from Stuttgart)

March:

  • Start WGLC/45 day public review period to publish an implementers draft
  • Spec is sent to Stuttgart to commence formal security analysis
  • Encourage implementers to implement & try interoping & provide feedback on spec
  • Request certification team implement IAE tests in VCI

Late April/May:

  • look at feedback, implement changes
  • move VP profile to VP spec (do we have an issue for tracking this?)
  • WGLC for VCI 1.1 as final if spec looks good. (Probably there would be an update to HAIP that allows/uses IAE as well)

Feedback very much welcome!

Metadata

Metadata

Assignees

No one assigned

    Labels

    iaeItems related to Interactive Authorization Endpoint

    Type

    No type

    Projects

    No projects

    Milestone

    No milestone

    Relationships

    None yet

    Development

    No branches or pull requests

    Issue actions